1, removal ingredient layer, Concrete mixing plants peripheral boards.
2, remove the feed layer roof, roof trusses and so the overall structure.
3, remove the screw conveyor and belt conveyor belt conveyor head mechanical parts and trusses (demolition should be preceded by roller machine, such as the above Mechanical parts removed).
4, removal of all mechanical equipment and ingredients layer ingredients podium.
5, bent on dismantling the control room and control room bracket.
6, remove the hopper and mixer and mixing layer corresponding platform stairs.
7, removal of mixing layer below the platform and the platform stairs, columns, etc..
8, Lever demolition aggregate bin and stationary concrete batching plant equipment.
9, removal of powder cans and above all the facilities, and then remove the powder cans bent below.
10, after cleaning all parts in inventory of what these devices in order to ensure that the equipment is complete and intact.